1、作業先前用手搬動飛輪,檢查傳動機構和工作裝置,調整間隙,堅固螺絲,確認無誤后啟動空運轉,檢查軸承應無異響,齒輪應嚙合良好。
1. Before operation, move the flywheel by hand, check the transmission mechanism and working device, adjust the clearance, firm the screws, and start the empty operation after confirmation. Check that the bearing should have the same sound and the gear should be in good engagement.
2、作業前檢查潤滑情況,按潤滑表規定進行潤滑;檢查三角皮帶松緊度;檢查各傳動機構有無異?,F象,若系旋轉刀盤剪斷式,則先運轉調直筒12分鐘,運轉正常后再起動切斷機構,同時檢查離合器是否靈活可靠。檢查電路和開關,線頭連接應牢固,保險絲應符合規定,電磁開關應接觸可靠,動作靈活,接地應良好。
2. Check the lubrication condition before operation and lubricate according to the lubrication table; Check the tightness of triangle belt; Check whether the transmission mechanism has abnormal phenomenon. If it is a rotary cutter head shearing type, run the straightening cylinder for 12 minutes first, and start the cutting mechanism after normal operation. At the same time, check whether the clutch is flexible and reliable. Check the circuit and switch, wire connection should be firm, fuse should meet the requirements, electromagnetic switch should be reliable contact, flexible action, grounding should be good.
3、在調直塊未固定,防護罩未蓋好前不得穿入鋼筋,以防機器開動后調直塊甩出傷人。
3, in the straightening block is not fixed, the protective cover is not covered before the reinforcement, in order to prevent the straightening block after the machine starts to throw out wounding.
4、切去不直的料頭或用錘頭敲直料頭,以利方便喂料;在導向筒前部安裝一根一米長的鋼管,先將要調直鋼筋穿過鋼管后,再穿入導向筒和調直筒,以防每盤鋼筋接近調直完畢時甩出傷人。
4. Cut off the non-straight material head or knock the straight material head with a hammer to facilitate feeding; Install a one meter long steel pipe in the front of the guide cylinder. After the straightening steel bar passes through the steel pipe, it is put into the guide cylinder and the straightening cylinder to prevent each plate of steel bar from being thrown out when it is close to straightening.
5、必須在停機的條件下進行鋼筋上盤、穿絲和引頭切斷或敲直。當鋼筋穿入后,手與曳引輥必須保持一定距離,不得接近,以防造成傷手事故。
5, must be stopped under the condition of steel plate, wire threading and lead head cut or straight. When the steel bar penetrates, the hand and the drag roller must keep a certain distance, not close to prevent hand injury accidents.
6、機械運轉中嚴禁打開各部防護罩及調整間隙,如發現有異常情況,應立即停機檢查,不得強行使用。
6, mechanical operation is strictly prohibited to open each part of the shield and adjust the gap, if found abnormal situation, should immediately stop the inspection, not forced use.
7、作業中要檢查各軸承溫度,是檢查調直筒軸承溫度,各軸承溫度不得高于60℃(以手摸能接受的熱度為限)。
7. The temperature of each bearing should be checked in the operation, especially the temperature of aligning cylinder bearing. The temperature of each bearing should not be higher than 60℃ (limited to the heat that can be accepted by hand)。
8、停機后應松開調直筒的調直塊回到原來位置,同時預壓彈簧也必須回位。
8. After stopping the machine, the aligning block of the aligning cylinder should be loosened to return to its original position, and the preloaded spring must also return to its original position.
9、鋼筋加工棚作業完后清理現場,機體上的污垢、灰塵,切斷電源,鎖好開關箱,并將調直切斷的鋼筋按規格分放整齊。
9. Clean up the site after the steel processing shed operation, remove the dirt and dust on the body, cut off the power supply, lock the switch box, and straighten the steel bar cut off according to the specifications.